Central plant optimization was an $11M project to provide a 4.5 MW peak power reduction that included chiller refurbishment, new VFDs, and a new building automation system to support thermal storage and chiller plant optimizations. Besides achieving the peak reduction, the project reduced over 9M kWh and was delivered under budget with over $4M in rebates and incentives.
Unique Strategy
Tuned thermal storage tank level sensors to improve thermal storage capacity.