Major Financial Institution


Download PDF

Chiller Plant Optimization

Chiller Plant

  • 2,800 Ton Plant
  • (4) 700 Ton Trane CVHF
  • (4) 75 HP CW Pumps
  • (4) 40 HP PCHW Pumps
  • Four secondary CHW loops

Project Scope

The optimization of the building systems involved a comprehensive sequence modification which allows the buildings systems to maintain occupant comfort and system performance while reducing the engineered systems energy consumption by over 20%.

Services

  • Controls Sequence
    • Chiller Plant
    • Boiler Plant
    • AHUs
  • Investment Grade Audit
  • Commissioning
  • Rebate Filing/Management
  • M&V

Value Added

Energy Rebate:

  • PA ACT 129
  • $55,312.32

Energy Savings:

  • Over $50,000 per year

Project Simple Payback:

  • Under 1.5 Years

Annual Energy Reduction:

  • Over 800,000 kWh

Efficiency Improvement:

  • Plant average efficiency reduced from 0.75 kW/Ton to 0.57 kW/Ton